BinaalineThe construction encyclopedia

Key points

  • IP code: the first digit is protection against solids (0–6), the second against water (0–9). X replaces a digit that is not required to be specified.
  • Zone 0: inside the bath or shower tray — only SELV equipment designed for it, at least IPX7.
  • Zone 1: above the bath/shower up to typically 2.25 m. Zone 2: extends 0.6 m horizontally beyond zone 1 and requires at least IPX4.
  • Ordinary sockets are not allowed within the zones, and bathroom circuits are protected by a 30 mA RCD.
Written for:OwnerContractor

A wet body offers less resistance to electricity, and a bathroom is wet by nature. So electrical standards give bathrooms a special section, IEC 60364-7-701, equivalent to section 701 of the British code BS 7671.

1) First: how to read an IP code

The IP code (degree of protection provided by an enclosure) is defined in IEC 605291:

  • First digit (0–6): protection against solid objects and dust.
  • Second digit (0–9): protection against water.
  • X: replaces a digit that is not required to be specified; it does not mean there is no protection (no protection is 0)2.
Second digitProtection against water
1Vertically dripping water
2Dripping water when tilted up to 15°
3Spraying water
4Splashing water
5Water jets
6Powerful water jets
7Temporary immersion up to 1 m
8Continuous immersion beyond 1 m
9High-pressure, high-temperature jets

Level names from the Electrical Installation Guide (Schneider Electric)2; immersion depths from a technical summary of IEC 60529 by an accredited test lab1. The exact test conditions are in the standard itself.

2) Bathroom zones

ZoneWhere?Basic requirements
0Inside the bath or shower trayOnly separated extra-low-voltage equipment (SELV: ≤ 12 V AC or ≤ 30 V DC) designed for this zone, at least IPX7.
1Above the bath/shower up to 2.25 m from the finished floor, or up to the highest fixed shower head if higher (in BS 7671)3Fixed equipment designed for this zone, at least IPX4.
2Extends 0.6 m horizontally beyond zone 1, to the same heightAt least IPX4.

Dimensions and the SELV condition are from the explanation of BS 7671 section 7013. Schneider Electric's installation guide summarises the protection per zone as: zone 0 = IPX7, zone 1 = IPX4 (IPX5 for showers with horizontal jets), zone 2 = IPX4, and all circuits outside the zones protected by a 30 mA RCD, an isolating transformer or SELV/PELV — noting this overview is based on the French code and the national code is the reference4. The binding reference in the Kingdom is SBC 4015.

3) Sockets in the bathroom

  • Ordinary sockets are not allowed within the zones. The British code BS 7671 (701.512.3), for example, prohibits them within 2.5 m horizontally of the zone 1 boundary, except SELV outlets and shaver supply units complying with BS EN 61558-2-5 (with an isolating transformer)3.
  • In the same code: zones 1 and 2 require at least IPX4, and all low-voltage circuits serving the bathroom or even passing through zones 1 and 2 must be protected by a 30 mA RCD (701.411.3.3)3. See the breakers guide.

4) Checklist when renovating a bathroom

  1. Fix the final bath/shower position first, then lay out electrical points based on the zones.
  2. Choose lights and extract fans with an IP rating suited to the zone.
  3. Ordinary light switches outside the bathroom or outside the zones.
  4. Make sure metal appliances (e.g. the water heater) are earthed and an RCD is present.
  5. The electric water heater is fed by a dedicated circuit sized by design.
Warning: any electrical work in a bathroom is for a qualified technician only. This guide is for understanding and planning.

Sources

The number next to a statement points to its source in this list. Sources back the general information; anything marked “practical advice” is editorial experience, not a quoted source. Anything that affects safety, structural design or electrical installations needs a licensed professional, and in Saudi Arabia the binding reference is the Saudi Building Code.

  1. 1IEC 60529 — Degrees of protection provided by enclosures (IP Code) — Applus+ Keystone
  2. 2Protection provided for enclosed equipment: codes IP and IK — Electrical Installation Guide (Schneider Electric) — Chapter E
  3. 3Bathroom Electrical Zones: BS 7671 Section 701 Zone Guide — Elec-Mate
  4. 4Bathroom electrical installation — Electrical Installation Guide (Schneider Electric)
  5. 5Saudi Electrical Code SBC 401 — code requirements (based on IEC 60364 with local amendments) — Saudi Building Code National Committee
Was this guide useful?
This guide is for general information and planning, based on standards and technical guides. Standards are revised periodically; in Saudi Arabia the binding reference is the Saudi Building Code and the instructions of the competent authorities. For design and execution, use a licensed engineer or technician. Found an error? Tell us.