BinaalineThe construction encyclopedia

Key points

  • A building permit application on Balady starts by selecting the plot's survey report; make sure it is available before buying.
  • A setback is the regulated zone between the property line and public or neighbouring property, and the building ratio is the permitted built area to plot area; the rules vary by subdivision and municipality.
  • Expansive soils cover about 37% of Saudi Arabia and sabkha is widespread on the coasts; a soil report before design is essential.
  • This guide helps you ask; it does not approve a specific plot.
Written for:Owner

Land is often the most expensive part of a project, and its mistakes cannot be fixed later. These are questions and documents to check before paying, with links to detailed guides.

Note: this guide does not judge a specific plot. That requires the plot documents, municipal review and an engineering office, and sometimes a lawyer for the contract.

1) Documents

  • Title deed: an updated electronic deed in the seller's name, with area and boundaries matching the ground (practical advice: ask a surveyor to check the boundaries on site).
  • Survey report: the Balady building permit service starts with the engineering office selecting the survey report for the plot1. Make sure the plot has one, or find out what is needed to obtain it.
  • Approved subdivision plan: plan number, plot number and land use (residential, commercial).

2) Building rules for the subdivision

Before buying, ask the municipality or an engineering office about the building requirements for this plot. Terms you will hear include2:

  • Setback: the regulated zone between the neighbouring private property line and public property.
  • Building ratio: the ratio of total permitted built area to the plot area.

These requirements, together with permitted floors and land use, vary by subdivision and city, so do not rely on what is said about neighbouring plots (practical advice). Commercial streets may have extra requirements; for example, shade regulations.

3) The site itself

QuestionWhy it mattersDetails
What is the soil?Expansive soils cover about 37% of the Kingdom3, and coastal sabkha may collapse when wetted and is corrosive4. A soil report before design sets the foundation type and costsoil and foundations
Where does rainwater go?A plot lower than the street or in a flood path collects waterwater around the building
Are services connected?Electricity, water and sewer; without them expect cost and delay (tank, cesspit, extensions)drainage, water tanks
Which way does it face?Affects sun, ventilation and entrancessun protection
What is on or under the plot?Fill, debris, power poles, services crossing the plotAsk the surveyor and engineering office

4) Checklist before paying

  1. An updated deed and boundaries checked on site.
  2. The survey report, or the steps to obtain it.
  3. Written building requirements for the plot (setbacks, building ratio, floors, use).
  4. An initial view on the soil, or a soil report for a large project.
  5. Status of services and rain drainage.
  6. Legal review of the purchase contract where needed.

After buying: the building journey from permit to occupancy certificate.

Sources

The number next to a statement points to its source in this list. Sources back the general information; anything marked “practical advice” is editorial experience, not a quoted source. Anything that affects safety, structural design or electrical installations needs a licensed professional, and in Saudi Arabia the binding reference is the Saudi Building Code.

  1. 1Issuing a Building Permit (e-service) — Balady platform — Ministry of Municipalities and Housing
  2. 2Regulatory Guide for Car Shades within the Property Line (2nd edition) — Riyadh Region Municipality
  3. 3Geotechnical characterization of expansive soils in Saudi Arabia: A regional review — Journal of Umm Al-Qura University for Engineering and Architecture (Springer)
  4. 4A review on the characteristics of sabkha soils in the Arabian Gulf Region — Arabian Journal of Geosciences (Springer)
Was this guide useful?
This guide is for general information and planning, based on standards and technical guides. Standards are revised periodically; in Saudi Arabia the binding reference is the Saudi Building Code and the instructions of the competent authorities. For design and execution, use a licensed engineer or technician. Found an error? Tell us.