Key points
- Plan the bath/shower and WC positions first; falls and electrical zones are built on them.
- Hidden work (water, drainage, electrics, waterproofing) is tested and photographed before being covered.
- Waterproofing under the tiles isn't optional, and is flood-tested before tiling.
- Choose tiles, adhesive and grout by specification, not just looks.
Written for:OwnerContractor
The bathroom is the smallest room in the house, but it brings together the most sensitive trades: water supply, drainage, electrics, waterproofing and tiling. This guide puts the work in clear stages and links each stage to its detailed, sourced guide.
Stage 1: Planning
- Draw a simple dimensioned plan: shower/bath, WC, basin, door, window/extract fan.
- If moving the WC or drain, first confirm the required falls can be achieved to the connection point.
- Mark the electrical zones from the shower position and place lights and sockets outside them. See bathroom electrics.
- Choose materials early (tiles, sanitaryware, mixers) because their sizes affect the services.
- Write a bill of quantities and specifications, and ask for detailed quotes. See the renovation checklist.
Stage 2: Strip-out and inspection
- Isolate water and electricity to the bathroom before starting.
- After strip-out, inspect: the concrete slab under the floor, signs of old damp, and the old pipes (especially galvanised steel). See rebar corrosion.
- Photograph everything you find; discoveries here can change the plan and the cost.
Stage 3: Hidden services
Water and drainage
- Choose the right pipe type for hot and cold lines. See pipe types.
- Keep to drainage falls and trap depths, and never remove venting.
- Fit a branch valve for the bathroom.
- Pressure-test the water supply and test the drainage before closing up.
Electrics
- Bathroom circuits are protected by a 30 mA RCD. See breakers.
- The water heater on a dedicated circuit, and lights and extract fans with an IP rating suited to the zone.
- Keep to standard wire colours. See wiring.
Before covering: photograph every wall and floor with its pipes and cables, with a tape measure visible. These photos will save you during any future installation or repair.
Stage 4: Floor and falls
- The shower floor needs falls towards the drain.
- Repair cracks and dips before waterproofing.
Stage 5: Waterproofing
- Use a liquid-applied membrane under the tiles complying with EN 14891, with reinforced corners and pipe outlets. See waterproofing under tiles.
- Flood test after drying and before tiling.
Stage 6: Tiling
- Tiles: for the bathroom floor prefer low-absorption tile with suitable slip resistance. See tile types and reading specifications.
- Adhesive: compatible with the membrane and suited to the tile type and size. See the adhesive guide.
- Coverage: 95% in wet areas and showers. See tile installation.
- Grout: CG2WA or epoxy for the shower. See the grout guide.
- Movement joints at corners and changes of plane are filled with mould-resistant sanitary silicone.
Work out quantities with the Binaaline tools.
Stage 7: Fixtures and finishing
- Install sanitaryware and mixers (a thermostatic mixer is preferred for the shower). See hot water safety.
- Install lights, extract fan, mirrors and accessories, avoiding piercing the membrane in the shower area where possible.
Stage 8: Handover
- Open all taps and watch drainage and for leaks under the basin.
- Pour water on the shower floor and check the falls and that no water ponds.
- Press the RCD test button.
- Tap the tiles gently to find hollow sounds. See tile problems.
- Collect warranties, material data sheets and photos of hidden work.
Was this guide useful?Thank you, your answer was recorded. If you found an error or a gap, report it from the link below.
This guide is for general information and planning, based on standards and technical guides. Standards are revised periodically; in Saudi Arabia the binding reference is the Saudi Building Code and the instructions of the competent authorities. For design and execution, use a licensed engineer or technician. Found an error? Tell us.